FORM 01 - CONSOLIDATED BUDGET (AS PER PLATFORM 5.1)

VERSION v3-CONSOLIDATED (TAKWARA/BNDES)

Project: Hands that Weave the Forest Duration: 48 months Estimated Global Value: R$ 25,380,957.00


1. COMPONENT: INDUSTRIAL INFRASTRUCTURE AND BIOECONOMY (TAKWARA 5.1)

Rubric Item Detailing Qty Unit Unit Value (R$) Total Value (R$)
Machinery and Equipment Biorefinery T02 Pyrolysis/Activation Unit (Ecopirol/Industrial) [5.1] 01 Unit 225,000.00 225,000.00
Conveyors/Mini-Loader Active Movement and Internal Logistics 01 Global 360,000.00 360,000.00
Tamboreador 5.1 Thermal/Abrasive Culm Sanding 02 Unit 135,000.00 270,000.00
Rotary Resinator Synchronized Multi-Axis Resinator 01 Unit 98,000.00 98,000.00
Cassette Press Universal Press for Bricks and OSB 02 Unit 185,000.00 370,000.00
Biocomposite Mixer Waterproof Concrete Mixer w/ PU Jet [5.1] 01 Unit 78,000.00 78,000.00
Jigs/Electrical Kits Assembly Systems and Industrial Tooling 01 Global 185,000.00 185,000.00
Works and Installations Acre Industrial Complex Shed, Earthmoving, and 3 Geodesic Domes 01 Global 1,835,340.00 1,835,340.00
Bio-industries (UBPs) Primary Beneficiation Units 05 Unit 285,000.00 1,425,000.00
Dry Sanitation (BSM) Modular Dry Toilets (Filter 5.1) 30 Unit 9,000.00 270,000.00
Consulting / HR Technical Team Coordination and Specialists (incl. benefits) 23 Per. 8,507,935.00
Learning Grants 30 Grant Holders (Tracks A, B, C) 30 Unit 52,800.00 1,584,000.00

2. COMPONENT: TRANSVERSAL SUPPORT AND MANAGEMENT (UNB/UFA/UFRR)

Rubric Item Detailing Qty Unit Unit Value (R$) Total Value (R$)
Specialized HR Researchers/Support Mobilization, Per Diems, and Technical Support 01 Global 1,425,000.00
Others Heavy Fleet Vehicles (CAPEX) and Fleet OPEX (48 months) 01 Global 3,495,984.00
Inputs and Reserves Working Capital, Inputs, Certifications, HSE, R&D 01 Global 4,694,698.00

FINANCIAL SUMMARY (WITH BUDGETARY RIGOR 5.1)

  • CAPEX (Asset Investment): R$ 6,964,240.00
  • OPEX (Operation, HR, and Reserves): R$ 18,416,717.00
  • TOTAL PROJECT (48 MONTHS): R$ 25,380,957.00

🎋 Takwara — Consolidated Budget V.2.1.0 Sourcing [5.1] applied to the integrated values of the Regenerative Amazon Platform.